Delay May Bar Judicial Review of Building & Development Permits in BC

When challenging a government decision through judicial review, timing can be just as important as the strength of the legal arguments. Courts have repeatedly emphasized that judicial review applications must be brought promptly, particularly where the decision being challenged affects public administration, local government processes, or the rights and expectations of others. Delay, however, does not automatically prevent a court from hearing a case. Instead, courts examine whether the delay was reasonable, whether there is a credible explanation supported by evidence, and whether allowing the review to proceed would undermine the need for certainty and finality in administrative decision-making. 

This article explores how British Columbia courts approach delay in judicial review proceedings, including the factors courts consider, examples of when delays have been excused, circumstances where late petitions were dismissed, and evidence supporting the reasonableness of delay.

I. The Law on Delay in Judicial Review of Building Permits

Jurisprudence strongly favours timely filing of review petitions respecting local government decisions, especially where there is statutory intent for expediency and certainty. Delays of months have been held as unreasonable, while delays of years have been held both inordinate and unreasonable. There are cases where petitions were not dismissed despite prolonged delays, but they are far, far fewer than cases on dismissal for delay. What follows is a breakdown of the law in this area, and please note that words such as “timeliness,” “delay,” “time-barred,” “barred by passage of time,” “effluxion of time,” and “dilatoriness” refer to the primary issue of delay in commencing a judicial review application.

In Beedie (Keefer Street) Holdings Ltd. v. Vancouver (City),[1] the petitioner Beedie Holdings Ltd. sought a judicial review, on grounds of bad faith and procedural fairness,[2] with respect to a decision by the City of Vancouver to deny a development permit application for a 9-storey mixed residential-retail building in Vancouver’s Chinatown neighbourhood.[3] Note the timeline: the City denied the application in November 2017, and Beedie filed the petition in August 2019. In March 2020, Beedie applied to have its petition converted into an action, but it was denied in September 2020. Beedie further appealed that decision in April 2021, and the petition was eventually heard in June 2022.[4] 

In this case, the City argued, amongst other things, that Beedie’s petition ought to be dismissed for delay, for Beedie allowed “over 21 months to pass after the…decision before filing its petition…,” and Beedie’s explanation for delay was unsatisfactory and accordingly prejudicial to the City.[5] Beedie argued that delay on its part was reasonable and justified, because City officials had indicated a desire to discuss with Beedie how the parties might avoid litigation,[6] and it had provided examples of correspondence “involving City officials and its representatives in which the City expressed an apparent willingness to consider alternative solutions.”[7] Beedie denied that the City was prejudiced by the timing of Beedie’s petition.[8]

The court applied section 11 of the Judicial Review Procedure Act (the “JRPA”)[9] as a starting point,[10] which, as discussed later on, provides that passage of time will not defeat a judicial review application unless “an enactment otherwise provides,” and the court considers that “substantial prejudice or hardship will result to [the City]” by reason of delay.[11] Crucially, however, the factors for reasonableness of delay favoured Beedie. The relevant factors in the analysis of unreasonable delay were:[12]

    1. length and reasons for delay;
    2. the extent to which delay undermines the objectives of the underlying administrative scheme;
    3. importance of the matter to the parties;
    4. hardship, prejudice, or injustice resulting from delay or dismissal of a potentially meritorious review; and
    5. interest of justice (collectively, the “Lowe Factors”).

I will return to these decisive factors later on, but in the interim note that the court considered these factors to Beedie’s favour:[13]

“[41]      … I conclude that this is not a case where I should exercise my residual discretion to summarily dismiss Beedie’s petition because of delay. In particular, the issue of whether the Project should be built on the culturally significant Property is critical to both parties. The delay cannot be said to undermine the City’s development permitting regime when it is apparent that the City was content to entertain post-Board decision discussions with Beedie that could have resulted in some form of development on the Property or elsewhere. I also do not accept that the City’s modification to the HA-1A zoning and its potential impact on the Court’s remedial authority on judicial review constitutes prejudice to the City that might justify a timeliness objection; if anything, it is Beedie, as the party seeking a remedy, that could be prejudiced by this legislative modification.”

In other words, the City’s delay arguments failed because both parties deserve clarity on the critical issue of the proposed building design being an appropriate fit within the neighbourhood’s cultural context; and there were contemporaneous discussions between parties for alternatives solutions to the denied development permit.

Beedie prevailed in this case: the petition was allowed, the City’s decision to dismiss Beedie’s application was set aside, and the City was ordered to reconsider Beedie’s application in accordance with the court’s ruling.[14]

II. Lowe Factors: The Common Law Test

Lowe v. Diebolt is the seminal case on the issue of reasonableness of delay in bringing judicial review proceedings. The Lowe Factors constitute the common law test for delay being a discretionary bar to judicial review. In Lowe, the petition was dismissed for six-month delay on grounds being unjustified considering this non-exhaustive list of factors.

The Lowe Factors must be weighed and assessed as a whole, for no single factor is determinative in assessing whether delay should result in a preliminary dismissal.[15]

The Lowe Factors were cited with approval in Powers v. British Columbia (Superintendent of Motor Vehicles),[16] where the court held the petitioner’s delay of 19 months to be unreasonable given the length of and lack of reasonable explanation for delay.[17] The petitioner did not adduce any evidence, let alone a reasonable explanation, to explain this delay. For clarity, there is no requirement in the Lowe Factors for the petitioner to adduce any type of evidence to show reasonableness of delay, but not doing so carries deleterious risk.[18] The court cited another case where the judge dismissed a petition to review a Provincial Court decision based on lack of explanation for delay.[19] Respecting the Lowe Factors, the court found the legislative intent in the underlying statutory scheme of having impaired drivers quickly dealt with was frustrated and undermined by the petitioner’s delay in seeking a review of the Superintendent of Motor Vehicles’ decision.[20] There was no issue of critical importance to be considered.[21] The unreasonable delay does not result in hardship or prejudice, and dismissal for reasons of delay would give effect, as intended, to the proper functioning of the administrative regime.[22]

III. Cases Where Delay Was Found Unreasonable

In Romegioli v. Langley (Township),[23] the court held the petitioner’s delay in seeking a review of bylaw infraction notices was “relatively short” in that his delay was only a month and a half after the 30-day time limit. Note that the petitioner prevailed on this point but the petition was ultimately dismissed with costs to the Township, because the impugned decision fell within the range of acceptable outcomes defensible in light of the facts and the law.[24]

On the spectrum’s other end lie instances such as a seven-year delay in bringing a judicial review application, where the petitioner had started multiple civil lawsuits during the delay period, but did not actually file a petition for review. [25] In Day v. Organization of Chartered Professional Accountants of British Columbia, the BC Supreme Court held the petitioner failed to adduce evidence justifying her delay in the prosecution of a filed petition: she had taken more than seven years to apply for review, and the Lowe Factors militated against the petitioner.[26] The original incidents underlying the late review occurred more than a decade prior,[27] meaning the prejudice and interests of justice factors cut against the petitioner’s position.[28] Further, while the factor of importance of the matter to the parties favoured both sides, the underlying administrative scheme provided for a 30-day time limit to bring a review of disciplinary decisions, thereby the legislation clearly favoured timely adjudication of disciplinary matters.[29] The BC Court of Appeal upheld this decision.[30]

Recently, in Sekyer v. British Columbia (Medical Services Commission),[31] the court applied the Lowe Factors to the petitioner’s detriment. In that case, the court considered the reasonableness of the petitioner’s seven-year delay in bringing a judicial review petition. The court noted the objectives of the legislation underpinning the BC Cancer Agency favoured timely medical treatment. The petitioner did not seek redress from the Ombudsperson, and barring such mitigating steps taken in the period of delay, the seven-year delay was “unjustifiable” in the circumstances and outweighed any financial prejudice to the petitioner may face if the petition were dismissed.[32] The petition was dismissed with costs.

In Dick v. District of Mission,[33] a delay of more than 10 years saw the petition dismissed, and was held to be “immoderate, excessive, and out of proportion to the complexity of the litigation.”[34] With the Lowe Factors applied, it was clear that the petitioner failed to take any steps in the intervening years, and failed to provide any reasonable explanation, even though the petitioner showed correspondences, which were wholly deficient in explaining such delay.[35] The petitioner’s evidence respecting his medical challenges failed to convince the court that his medical issues were, on a balance of probabilities, such that it precluded him from advancing the litigation.[36] Further, an “inordinate and unexplained” 10-year delay did not rebut the common law presumption of serious prejudice to the respondents if delay was allowed.[37] In other words: longer the delay, stronger the prejudice to the respondent.

Similarly, the court applied the Lowe Factors in Mawani v. Dobbs to hold that, where a 60-day time limit was clearly prescribed, a 10- or 11-month delay in filing the petition was unreasonable, thereby necessitating the court’s exercise of discretion under section 8 of the JRPA to dismiss the petition on that ground.[38]

To further dwell on this point, I would say that having evidence of being involved in other legal proceedings, related to the subject matter of the review or otherwise, is not evidence of reasonable explanation.[39] In fact, where the petitioner takes all necessary steps in other proceedings, an adverse inference may be drawn from this fact alone: to the court’s eyes, and as the respondents are likely to assert, the petitioner had the time and the know-how to initiate and conduct other types of litigation in relation to the underlying matter, but chose, nevertheless, not to bring a judicial review proceeding in that time. This happened in Green v. Bentz, and the respondents in that case prevailed on their assertion that the petition warranted dismissal for lack of “reasonable explanation for the considerable delay.”[40]

The petitioner’s conduct during the delay period is also of notable consequence to the analysis. Take, for instance, Smith v. British Columbia (Attorney General).[41] In that case, the petitioner sought to (a) set aside a trespass notice and a decision by the provincial forest Ministry disallowing his application to occupy Crown land for private moorage purposes, and (b) compel the Ministry to issue a permit and reconsider his application from 2010 respecting a private moorage dock tenure. The respondent Ministry sought dismissal for delay. The petitioner engaged in conduct that was “entirely inappropriate”[42] in that he actually constructed a dock without authority to do so, did not prepare for the possibility that his applications to construct his dock would be disallowed, failed to seek a timely review of the decisions and notices issued in 2010, 2012, and 2018, and wrongly assumed that the respondent Ministry had dropped the matter in the intervening period.[43] The “functional integrity of the legislative schemes at issue and the quality of subsequent decisions made under these schemes” were undermined by his delay.[44] While he may be prejudiced by dismissal, the evidence going to conduct overall titled the Lowe Factors against the petitioner.

Similarly, where one has the time to prosecute one type of legal proceeding (say, a human rights complaint), there that person is presumed capable of commencing a judicial review proceeding (notwithstanding, for instance, the fact that they may be homeless during that delay period).[45]

Further, evidence of mere intention to seek a reconsideration or judicial review of a decision is not, in any measure, evidence of reasonable explanation for delay in filing.[46] Reliance on counsel’s advice as a reasonable reason for delay is unlikely to succeed in instances where the statutory time-limit have elapsed prior to retaining counsel.[47]

Delay is likely to be considered unreasonable if it is only explained by the evidence from the petitioner themselves.[48] Consider Chiodo v. John Doe.[49] There, the BC Court of Appeal upheld the reviewing judge’s exercise of discretion to deny relief based on undue delay. The court noted that the reviewing judge was alive to, and weighed, the prejudice to the petitioner if the petition was dismissed, but found that the petitioner “failed to explain” the eight-month delay.[50] That the petitioner misunderstood counsel’s words, or that the petitioner erroneously understood relevant administrative processes, were ultimately of no consequence in the court’s consideration of the explanation tendered for an eight-month delay.[51]

Now, take Toor v. British Columbia (Superintendent of Motor Vehicles) for the proposition that the “question of whether delay will operate to bar a judicial review is fact specific and involves a balancing of the factors set out in Lowe and the cases considering it.”[52] There, while the petitioner’s evidence struggled to explain delay, a finding that weighed against her, it was held that the petitioner did adduce evidence of prejudice or hardship from the dismissal for delay reasons.[53] Unfortunately for the petitioner, the deference to the statutory scheme’s objectives won the day.

In Kawakami v. Brayer,[54] a constellation of factors led to the finding that the petitioner’s delay was unreasonable and unexplained. Though the petitioner adduced affidavit evidence in support of her delay, such evidence centred around access to counsel, and a close examination of the affidavit evidence showed that the petitioner had contacted about 12 lawyers, but actually corresponded with only one, and she had contacted these lawyers around the time of a settlement conference prior to the review proceeding, which supported the inference that she had the time to contact counsel for settlement purposes but she neglected to do so for judicial review purposes.[55] The statutory scheme, the case law, and the respondent’s need for finality of decision (that was rendered by a Small Claims court eight months prior) were factors that cut against her position as well.[56] Her eight month delay was, therefore, was the basis for dismissal.[57]

IV. Cases Where Delay Was Excused

That said, there are some recent precedents were lengthy periods of delay have been ruled as reasonable. Consider A.R.S. Trucking & Welding Limited v. BC (Transportation and Infrastructure),[58] wherein the petitioner sought review of two decisions of the Minister of Transportation and Infrastructure respecting the revocation and denial of permits. The petitioner’s lengthy period of delay—that of 26 months from the date of the first decision, and four months from the date of the second decision—was, in fact in these circumstances, reasonable. The court did not find the petitioner to be at fault for the 10-month delay between the filing of the petition and the start of the hearing, and the 16-month delay prior to the filing was explainable in that evidence showed the petitioner was attempting to resolve the matter without resorting to litigation.[59] The delay of four months with respect to the second decision was attributable to the Ministry.[60] Further, evidence of significant prejudice to the petitioner should the petition be dismissed militated in the petitioner’s favour: there was “uncontroverted evidence” that the petitioner stood to lose $300,000 per month should the petitioner be denied to operate their trailers.[61] The respondent Minister’s request for dismissal based on delay was denied, and the Minister’s decisions were set aside and remitted for reconsideration.[62]

Recently, in Galiano Forest Lot Owners Association v. Galiano Island Local Trust Committee, the BC Court of Appeal refused to exercise its discretion to dismiss the petition for delay by applying the Lowe Factors.[63] There, while the indicum of legislative intent that challenges to bylaws should be brought in a timely manner was present, “a number of unique features of the present case that pull in the other direction.”[64] Briefly put, the prejudice considerations favoured the petitioner and other residents of Galiano Island, with whom lied a strong public interest in the adjudication of a “longstanding controversy over the validity and applicability of [the impugned bylaw] to private managed forest lands.”[65] Note that the petitioner filed the petition six months after receiving the bylaw notice. Therefore, a six month delay in this recent case was allowed.

Of brief note is Wells v. Victoria (City), where the petitioner ultimately failed on the adjudication of an impugned bylaw’s validity, but the court noted that time requirements in the LGA are “extremely short…and are not relevant to a consideration of general delay.”[66] In that case, the petitioner’s delay was short, to the tune of weeks, between the issuance of a development permit and a judicial review challenging the same.[67]

This is echoed in Thandi v. The Police Complaint Commissioner of British Columbia, where respecting the common law permissibility of delay the court noted:[68]

“I note that delays of less than 11 months have been considered unreasonable in some circumstances, such as in Lowe and Kawakami. On the other hand, there are many other authorities that have excused delays of much longer duration. The length of the delay is but one of the factors to consider.”

In that case, the petitioner’s 11-month delay was prima facie unreasonable in light of the statutory scheme that signalled limited tolerance for delay.[69] Other than assertions from counsel at the hearing, the petitioner failed to adduce proper evidence of medical issues. The petition was dismissed for unreasonable delay.

V. What Does Not Constitute a Reasonable Explanation for Delay

Thus, the time limit issue turns on the reasonableness of delay. The strength of the evidence dictates the reasonableness of delay. To assess justification for delay, the court will consider evidence from your side, but your case will be stronger if there is third party evidence corroborating your reasons for delay. The court will weigh your reasons for and the length of delay, the objectives of the applicable legislation and the extent to which your delay undermines such objectives, your interests in the case, the hardship, prejudice, or injustice resulting from delay or the dismissal of what might be a meritorious review, and the interests of justice. At common law, there is an obligation on you, as the petitioner, to act promptly with respect to filing the petition and seeking a hearing right away. The law treats delay of 30-days or thereabouts to be reasonable, but delays of five (5) years is considered unreasonable and prejudicial. To borrow the words of Justice Groberman in Lowe, your delay in the order of months in bringing a judicial review proceeding, while arguably lengthy, is not, in and of itself, fatally prejudicial to you, though it is bound to add “incrementally” to any existing prejudice.[70]

Where the legislative schemes depend on certainty and finality, delay in seeking a judicial review may be seen by courts as causing serious jeopardy to the functional integrity of the schemes and quality of decisions made pursuant to the same.[71] Time and again, the court has dismissed petitions for delay in seeking review of local government decisions, primarily because the statutory scheme of the LGA prioritizes expediency.

VI. Importance of Evidence Explaining Delay

Case law is clear that allowing a petition despite delay depends entirely on the reasonableness of delay, which must be explained, in fact well explained by evidence, preferably third party or external evidence of reasons for delay. There is heavy judicial emphasis on adducing proper explanation for not acting promptly, because the court is sensitive to the prejudice to parties to the proceedings. The presumption of prejudice from delay is stronger in the absence of any explanation.[72] In other words, if you can satisfactorily explain[73] the delay of over 11 months, then you successfully rebut the common law presumption of prejudice from prolonged delay.[74]

This aspect of reasonableness (beyond the enumerated factors) may be the highest hurdle to clear. Case law is not clear as to what evidence constitutes acceptable evidence, rather cases provide types of evidence are inadmissible. Rejected evidence often centre around the petitioner’s inability to attend. Where petitioners have stated health reasons, which, in itself is a high bar to meet, they are undone by judicial logic to the effect of “if one is well enough to do X, one is presumptively well enough to file the petition in time.” Where petitioners have pointed to ongoing litigation as the reason for delay, they are met with similar judicial logic to the effect of “if one is competent or funded well enough to litigate, then one may be presumptively expected to file a petition for review in time.” Therefore, proper explanation for delay is the key.[75]

VII. Concluding Thoughts

The rules surrounding delay in judicial review proceedings are highly fact-specific, and a seemingly minor delay can have significant consequences if it is not properly explained and supported by evidence. Whether a court will permit a late-filed petition depends on the circumstances of the case, the applicable statutory scheme, the reasons for delay, and the overall interests of justice. 

If you are considering challenging a decision made by a government body, local authority, tribunal, or other administrative decision-maker, obtaining legal advice as early as possible is critical. Sam Bhattacharjee assists clients in judicial review matters by assessing potential claims, identifying procedural risks, and developing strategies to present the strongest possible case before the court. Contact Sam for advice on your options and the steps required to protect your right to seek judicial review.


[1] Beedie (Keefer Street) Holdings Ltd. v Vancouver (City), 2022 BCSC 2150 (“Beedie”).

[2] Beedie at para 2.

[3] Beedie at paras 2-4.

[4] Beedie at paras 29-32.

[5] Beedie at para 37.

[6] Beedie at para 38.

[7] Beedie at para 38.

[8] Beedie at para 38.

[9] Judicial Review Procedure Act, [RSBC 1996] Chapter 241 (the “JRPA”), s. 11.

[10] Beedie at para 39.

[11] JRPA, s. 11.

[12] Day at para 20 citing Lowe at para 46.

[13] Beedie at para 41.

[14] Beedie at paras 7, 112, and 113.

[15] Toor v British Columbia (Superintendent of Motor Vehicles), 2020 BCSC 1701 (“Toor”) at paras 19-21.

[16] Powers v British Columbia (Superintendent of Motor Vehicles), 2018 BCSC 1289 (“Powers”).

[17] Powers at para 53.

[18] Powers at para 30.

[19] Housewise Construction Ltd. v. Whitgift Holdings Ltd., 2016 BCSC 2245 (“Housewise”).

[20] Powers at paras 32-38.

[21] Powers at para 50.

[22] Powers at paras 51-54.

[23] Romegioli v Langley (Township), 2018 BCSC 1867 (“Romegioli”).

[24] Romegioli at paras 37-39.

[25] Day v. Organization of Chartered Professional Accountants of British Columbia, 2018 BCCA 495 (“Day Appeal Decision”).

[26] Day at para 20.

[27] Day at para 29.

[28] Day at paras 28-38.

[29] Day at paras 21-27.

[30] Day Appeal Decision.

[31] Sekyer v British Columbia (Medical Services Commission), 2025 BCSC 1434  (“Sekyer”).

[32] Sekyer at para 54.

[33] Dick v District of Mission, 2022 BCSC 1677 (“District of Mission”).

[34] District of Mission at para 37.

[35] District of Mission at paras 39-42.

[36] District of Mission para 41.

[37] District of Mission at para

[38] Mawani v Dobbs, 2022 BCSC 1285  (“Mawani”) at para 29.

[39] Green v Bentz, 2019 BCSC 1603 (“Green”) at paras 9-17.

[40] Green at para 17.

[41] Smith v British Columbia (Attorney General), 2019 BCSC 2190 (“Smith”).

[42] Smith at para 63.

[43] Smith at paras 38-73.

[44] Smith at para 59.

[45] Green v. Barry, 2017 BCSC 2316.

[46] Denton v. British Columbia (Workers’ Compensation Appeal Tribunal), 2017 BCCA 403 (“Denton”) at para 30.

[47] Denton at paras 27, 29, and 31.

[48] Toor at para 23 citing Foster v British Columbia (Superintendent of Motor Vehicles), 2018 BCSC 1194 at paras 16, 39.

[49] Chiodo v. John Doe, 2022 BCCA 33 (“Chiodo”).

[50] Chiodo at para 15.

[51] Chiodo at paras 9-22.

[52] Toor at para 47.

[53] Toor at paras 33-45.

[54] Kawakami v Brayer, 2021 BCSC 267 (“Kawakami”).

[55] Kawakami at para 31.

[56] Kawakami at paras 28-34.

[57] Kawakami at paras 36 and 37.

[58] A.R.S. Trucking & Welding Limited v BC (Transportation and Infrastructure), 2023 BCSC 1486 (“A.R.S. Trucking”).

[59] A.R.S. Trucking at paras 100 to 104.

[60] A.R.S. Trucking at paras 105 and 106.

[61] A.R.S. Trucking at paras 107.

[62] A.R.S. Trucking at para 133.

[63] Galiano Forest Lot Owners Association v. Galiano Island Local Trust Committee, 2025 BCCA 15 (“Galiano Forest Lot Owners Association”) at para 53.

[64] Galiano Forest Lot Owners Association at para 50.

[65] Galiano Forest Lot Owners Association at para 52.

[66] Wells v Victoria (City), 2019 BCSC 2267 (“Wells”) at para 49.

[67] Wells at paras 48 and 49.

[68] Thandi v The Police Complaint Commissioner of British Columbia, 2022 BCSC 77 (“Thandi”) at para 91.

[69] Thandi at para 95.

[70] Lowe at para 71.

[71] Smith at para 54.

[72] Powers at paras 30 and 31.

[73] Day at para 40: “In P.P.G. Industries Canada Ltd. v. Canada (Attorney General), 1975 CanLII 204 (SCC), … at 749, the Supreme Court of Canada made it clear that the lack of an explanation for a delay in pursuing a judicial review weighs especially in favour of finding it unreasonable.” District of Mission at para 46.

[74] District of Mission at para 46.

[75] Powers.